One printing station must finish an order of 1,260 posters by 6:00 pm. Its regular operator works from 9:00 am until 1:00 pm, producing 180 posters an hour at a constant rate, then leaves unexpectedly. Only one operator can use the station at a time.
A replacement can print 240 posters an hour, but is free to choose when to start after 1:00 pm. Assuming neither operator has downtime once working, how long must the replacement print, and what is the latest start time that still finishes the order before closing?
Get hint
Hint 1
The replacement is responsible for the unfinished posters, not the original 1,260.
Show solution
The first operator works four hours, completing \(4\times180=720\) posters. The unfinished workload is \(1{,}260-720=540\) posters. At 240 posters per hour, the replacement needs
\[
\frac{540\text{ posters}}{240\text{ posters/hour}}=\frac94\text{ hours}=2\text{ h }15\text{ min}.
\]
Starting at 3:45 pm provides exactly 2 hours 15 minutes until the 6:00 pm deadline. Starting any later misses the deadline because capacity is fixed and there is no overlapping work. Reconciliation: \(720+240(9/4)=1{,}260\) posters. Adding hours worked by unequal-rate operators would not preserve the units of the workload.
Assumptions
The job size is fixed and completed posters are additive.
The station has a single active operator; rates are constant and printing can start at any time after 1:00 pm.
Final Answer
\(2\) hours \(15\) minutes; latest start 3:45 pm.